Speed up install exhausted gas treatment gas duct outside insulation
Mill entrance conveyor B2 single commissioning finished
Install and commission 2# raw mill main motor
At present, Anhui Wuhu Conch Ⅲ phase 12000t/d clinker line contracted by our company just strive for the fire target, overcome all obstacles, overtime to speed up progress, meanwhile, ensure project quality. Until to April 25th, all main gutters are connected in plant, all electrical rooms are energized, raw mill and cooler refractory installation finished, tertiary air duct refractory is under construction, erection work just near to the end. To ensure fire and produce cement as schedule, project staff unity to go all out to achieve the fire target.